PSTN Switch Off 2027: Business Readiness Guide

UK PSTN switch-off

2027 business readiness guide. Sources checked 2 October 2026.

Start your PSTN migration with three practical tasks: inventory every line and connected device, agree tests with the people who maintain them, and confirm a migration plan with your phone provider. Include alarms, lift emergency phones and payment terminals alongside office calls. A working desk phone does not prove that the rest of your site is ready.

For the PSTN switch off 2027, Openreach currently identifies 31 January 2027 as the retirement date for the old network. Your own service may change earlier. Record the provider-confirmed date for each line, resolve unknown dependencies and test the replacement before authorising the change.

This guide and its downloadable PSTN readiness checklist help UK business owners, IT teams and facilities managers organise that work. They are a planning framework; equipment suppliers must confirm compatibility and any safety, maintenance or contractual requirements for the actual installation.

What the UK Landline Switch Off Means for 2027

The Public Switched Telephone Network (PSTN) is the traditional telephone network being replaced by IP-based services, including Voice over Internet Protocol (VoIP). ISDN is a separate legacy digital telephone service that also needs migration. The change concerns the service and its dependencies; it does not mean that every copper cable or every landline number disappears on one day.

Openreach’s business notice of 31 July 2026 confirms PSTN retirement on 31 January 2027. Ofcom’s digital landline guidance, updated 26 August 2026, distinguishes the BT Openreach network from other operators’ networks. It says other operators also plan retirement, but their dates have not yet been set. Confirm which network supplies each service rather than applying the BT date to every UK line.

Government guidance on the digital landline transition explains that this is an industry-led change and the migration process depends on the communications provider. Treat the national programme date as context, and your provider’s written arrangements as the basis for scheduling each site.

Openreach’s business switchover guidance warns that a business which has not migrated may lose service or move to temporary emergency voice-only access. Do not treat that temporary provision as a plan for business calling, broadband or connected equipment.

1. Inventory Every Line and Connected Device

Reconcile telecoms bills and contracts with a walkthrough of each premises. Ask IT, facilities, security, finance and the landlord about systems they manage. Identify unused-looking lines before cancelling them: one line may serve more than one device, and a service label may be out of date.

Openreach specifically recommends checking alarms, CCTV, payment terminals, door entry, lift emergency phones and fire alarm monitoring. Add fax, telemetry, lone-worker or telecare equipment where present. These are prompts to investigate, rather than a claim that every example uses PSTN.

PSTN inventory: create one record per line and one per dependent device
Asset or line Details and evidence to record Status and owner
Office phones / PBX / ISDN Site, number, provider, service type, phone-system model, required call features and linked broadband Confirmed / investigate; named IT or telecoms owner
Fire or intruder alarm Panel and communicator model, line reference, maintainer, monitoring centre and signalling requirements Confirmed / investigate; facilities and alarm maintainer
Lift emergency phone Lift location, communicator model, rescue contact route, power backup and maintenance provider Confirmed / investigate; building owner and lift contractor
Payment terminal Terminal model, connection type, merchant provider and approved transaction test Confirmed / investigate; finance or retail operations
Other connected systems Door entry, CCTV, fax, telemetry, telecare or lone-worker system; purpose, connection and supplier Confirmed / investigate; responsible system owner

For every record, add the replacement route, provider-confirmed change date, next action, action deadline, evidence reference and test result. “Confirmed” means the relevant fact is supported by evidence; it does not mean the whole migration is approved. Leave uncertain items as “investigate” and assign an owner.

2. Resolve Dependencies with the Right Suppliers

Send the inventory to your phone provider and each equipment maintainer. Ask specific questions and retain dated written answers:

Ofcom’s letter to providers dated 29 January 2026 highlights business alarms, telemetry and monitoring equipment that may need replacement or reconfiguration because IP services may not reproduce PSTN characteristics such as line powering. It also notes that business-supplied lines can serve vulnerable end users, including telecare users.

If your premises has safety-related equipment, involve its competent maintainer before changing connectivity. Ask them to identify the applicable standards and acceptance criteria, and check any relevant insurance conditions with your insurer or broker. This guide does not prescribe a universal alarm transmission grade, lift battery runtime or insurance outcome.

Plan Power and Connection Resilience Separately

Digital voice depends on powered equipment. Review the whole chain: router, fibre termination where installed, switches, phone system, adapters and the connected device. A battery on one component does not establish that the complete path will work.

Ofcom’s January 2026 letter discusses a minimum one-hour emergency-call solution for landline-dependent customers under its power-cut guidance, including proportionate protection for dependent business customers. That is emergency access guidance, not a runtime specification for every business system. Agree the required duration and fallback with the provider and device maintainer. Where mobile backup is proposed, check signal at the actual installation and test the intended route.

3. Select and Test the Replacement

Choose voice and non-voice solutions separately. An analogue telephone adapter provides a socket, but that alone does not establish device compatibility, monitoring performance or power resilience. Obtain confirmation for the exact configuration and test the end-to-end service.

For office calling, review Vertu Connect’s SIP trunking if you are considering connecting a compatible phone system over IP. Its service page describes compatibility review, number-porting coordination and incoming and outgoing call checks. For teams assessing external calling within Teams, see Microsoft Teams calling. Compare the wider voice options on the unified communications page. Confirm licensing, capacity, portability, device support and resilience for your proposed setup.

A voice platform does not replace the specialist assessment of an alarm, lift or payment terminal. Ask its supplier whether the device needs reconfiguration, replacement or a different supported connection.

Record the date, configuration, tester, expected result, actual result and unresolved fault. Arrange tests of safety systems with the maintainer and monitoring centre; do not disconnect them for an informal trial. Ask your phone provider how to verify emergency-calling arrangements without placing an unarranged test call to 999 or 112.

4. Agree the Migration and Number-Porting Plan

Use the provider-confirmed dates and supplier lead times to build the schedule. Avoid a generic countdown: installation, access, equipment work and number porting may follow different arrangements at each site.

  1. Confirm which services change together and whether a number transfer will cease a line or affect linked broadband.
  2. Agree the porting information, transfer date, expected disruption and any temporary call handling with the gaining provider.
  3. Make the replacement connection, configuration and device work ready for the agreed tests.
  4. Assign an owner for go-live, supplier attendance, escalation and the decision to proceed or defer.
  5. Record a feasible fallback or recovery plan. Do not assume an old service can be restored after it is ceased.
  6. Notify staff and affected users of the change and the support route.

Do not independently cancel a line simply because the new phones work. Confirm the provider’s transfer and cancellation sequence, and obtain acceptance for every dependent system. Parallel operation and diversions may help where available, but their suitability and timing need provider agreement; neither guarantees uninterrupted service.

5. Complete Post-Change Checks

Repeat the agreed voice and device tests after the actual change. Check that monitoring destinations receive signals, call routes reach the right teams and approved fallback works in the migrated configuration. Resolve failures with the relevant supplier and keep the evidence against the inventory.

Update diagrams, asset records, service contacts, contracts and battery-maintenance responsibilities. Confirm that obsolete services are ceased only through the agreed process, then review bills for unexpected ongoing charges. Set future testing and maintenance intervals with the system maintainers.

When SIP trunking is part of your migration, take the 15 questions to ask a UK SIP trunking provider into the supplier discussion. The guide helps turn porting, compatibility and continuity answers into a verification plan.

If your chosen route is SIP, use the SIP trunking migration checklist and worksheet for the detailed number inventory, call-capacity assumptions, resilience tests and go/no-go decision. Keep its porting and recovery record alongside your wider PSTN readiness plan.

Download the PSTN Readiness Checklist

Use the three-page PSTN migration checklist below to assign actions, record dependencies and capture test evidence. It includes an inventory worksheet and source dates. The same five action groups are available as text on this page for keyboard and screen-reader access.

PDF · 3 PAGES · 2027 EDITION

Your Business PSTN Readiness Checklist

Keep inventory, supplier questions, testing, migration and post-change checks together in one printable worksheet.

Download the PSTN Checklist

Opens the PDF in a new tab. Print at actual size on A4. Use the text checklist below if you prefer an accessible on-page version.

Accessible PSTN Readiness Checklist

Copy these actions into your own records. For each action, record confirmed or investigate, owner, target date, evidence and check date. Where an action does not apply, record the reason.

  1. Inventory: reconcile bills, contracts and a site walkthrough; identify every line, number and connected device; record location, purpose, provider, model, criticality and owner.
  2. Dependencies: confirm the network and service-change date; get model-specific supplier requirements; identify shared lines, power needs, broadband dependencies, vulnerable users and fallback arrangements.
  3. Testing: agree voice and device acceptance tests; verify the actual destination receives calls or signals; have suppliers arrange controlled failure and restoration tests; retain results and resolve faults.
  4. Migration: agree installations, number porting, linked-service effects, change window, escalation and recovery; obtain acceptance before proceeding; follow the provider-agreed cancellation sequence.
  5. Post-change: repeat tests in the live configuration; update records, contacts and maintenance responsibilities; verify billing and arrange future checks.

Assumptions and source dates: the BT-network retirement date of 31 January 2027 was checked against Openreach’s 31 July 2026 notice and Ofcom’s 26 August 2026 guidance on 2 October 2026. Your line dates, compatibility, lead times and backup duration remain supplier-specific and must be rechecked before ordering and cutover. The checklist is a practical synthesis, not a device certification or a completed site assessment.

Your Next Step: A No-obligation Readiness Review

Bring your completed inventory, outstanding supplier questions and proposed migration dates to a consultation. Book a consultation with Vertu Connect to review your PSTN readiness and migration questions. Include your equipment maintainers where specialist systems need confirmation.

Sources and Review Scope

Sources checked on 2 October 2026: Openreach’s business switchover guidance and 31 July 2026 notice; Ofcom’s digital landline guidance updated 26 August 2026 and provider letter dated 29 January 2026; and government transition guidance. Ofcom’s household guidance is used for network context and power/telecare risks; the business discussion also draws on its provider letter. Vertu Connect service pages were checked for the advertised voice options, without treating marketing claims as compatibility or continuity guarantees.

Recheck official guidance and the provider-confirmed plan before a change. Review this guide monthly while migration is in progress and after a material Openreach or Ofcom update.

Prepare Your Business for the PSTN Switch-Off

Get a clear migration plan for your phone system, business numbers and critical analogue devices. Button: Explore Unified Communications

Explore Unified Communications

Join The Conversation

  1. Robin Lane says:

    How do you check a backup connection actually keeps phones and card payments working when the main line drops?

    1. Alex Morgan says:

      Test it during an agreed quiet period: disconnect the main connection, then try calls and a payment over the backup. Record the interruption and any dropped sessions. Restore the main line and check it switches back cleanly. A ‘backup connected’ light alone doesn’t tell you those services work.

      More detail: Fibre vs Satellite Internet: A 2026 Guide for UK Businesses.

  2. Harper Foster says:

    Our broadband shares the same copper line as the phones — does moving the number to VoIP cut the broadband off as well?

    1. Jamie Morgan says:

      Yes, it can. Where broadband rides on the same copper pair, porting the number to VoIP typically ceases the old line and takes the broadband with it. Ask your provider to re-provision broadband as a standalone data-only service (such as SOGEA) before the port, and get the sequence confirmed in writing. A business broadband checklist can help you record those dependencies before authorising any closure.